Done, done, done (a bit late)

Posted by Jeffrey on Jul 27, 2009

So, I was so excited to be done the whole reno thing that I forgot to post! Well, in hindsight, it just seemed like we would get really close to being done then something would crop up to push back the completion date a bit further out. Truth be told, it does feel really good to be done and have the rest of the summer to enjoy the house!

When the tile was at last done and the plates were put on the switches, we realized that looking at our punch list that there were no more things left to cross off! And just in time too as we had some friends over on the weekend to “break in” the results.

In terms of impact the work that was done in the kitchen was huge no question. But everyone commented on the new hardwood and the paint as making a big difference to the rest of the floor. Which goes to prove that for the biggest bang for the buck, changing the paint color is usually the way to go to improve your space.

So now to go over some of our choices and how they are holding up in use. First of all, lets start from the bottom up and take a look at the flooring. Everyone agrees that it is really gorgeous. Hickory would not have been the first material on my lips if you’d have asked me a year ago about hardwood, but it looks really elegant. It gives the visual interest you want in a floor with the grain pattern, but not too busy as you get with other hardwoods.

The color also goes really well with our furniture (and the paint, but that’s another story). The only thing I have to get used to is the scratch factor. I still kind of worry about scratching the floor and I know, I know that this is inevitable, but I haven’t gotten over it yet. And even though the manufacturer quotes a “35 year warrantee” and a high tech “Nano” coating it still scratches (all floors do!). In fact my contractor said that he’s never heard of anyone collecting on any manufacturer’s warrantee!

But that’s not really the point here. Our intention was to get a good looking floor to carry through the entire space to unify the living/dining room and the kitchen. I know the contractor thought we were crazy to put hardwood in the kitchen instead of ceramic, we love it! And the new carpet should help with the entry areas.

Carpet looks great with the paint and hardwood!


Speaking of carpet we selected a great fabric from D’Abbieri Collection called “Leggero – Undercool” and it feels really luxurious underfoot. The carpet installer (Victorious Flooring) did a fantastic job doing the stair runner and the front hall. He even set up the cutting so that we could maximize the carpet installation within the least amount of carpet saving us about $400 in the process!

So next time I will get into some detail on some of the fixtures in the kitchen proper and maybe sum up our experiences.


A few things to wait on to finish the reno

Posted by Jeffrey on Jun 4, 2009

The stucco guys were here today to patch the area where the bricklayer filled in the windows. Tomorrow (I hope) they’ll be back to scratch coat the entire wall to even it out. Judging by the mess today just from the patch, the next coat will be messy…. Very messy.

But we are still waiting on a few things. The tile contractor has to take a look at the backsplash to give us an opinion on the job and the electrician has to come and put in the trims for the potlights and all the plates on the switches. And in the kitchen we couldn’t push the stove all the way back- it is just about ¾” out too far and it interferes slightly with the door mounted spice rack beside the stove. Maybe we can figure it out later.

Slide in stoves don’t always slide all the way.


We still are putting things back in the cupboards and deciding if they are in the right place. We never really thought of it before as we were so short of space that organization was an afterthought. In this case we can hopefully think of what makes sense in the way we work and organize accordingly. But I think we will just run out of patience and put stuff back and worry about it later. Anything to get rid of those boxes!

But the floor looks good.


On the weekend I finished painting the ceiling and the one area on the wall that’d been holding us up and we ripped off some of the kraft paper that was protecting the floor. I’d forgotten how good the floor looked! But it reminded me that we still have to get some carpet or runners done for the front hall and near the back door. So with that in mind, we went to a store to select a carpet sample and lo and behold within five minutes we found one we both agreed on.

Got the drapes up-finally.


So now it’s a case of finding someone that can do the custom work to cut around all the vents etc that are in the front hall.

I just finished painting the walls in the kitchen and just have the second coat to do near the stairs – almost done! When I said I would do the painting, I seem to have forgotten how much time it takes. At least the paint I’m using is good (Aura by Benjamin Moore) so it makes it a bit easier to cover the last of the yellow.


Finalizing construction drawings

Posted by Jeffrey on Mar 9, 2009

Since we signed the contract, we have been moving forward to get the schedule locked down and all of the drawings for the cabinets in place so they can be sent to the cabinet makers to get started.

On Friday I was supposed to finalize the drawings with my comments, but came down with brutal flu bug and stayed in bed basically for 36 hours. After the weekend [and feeling much better] I am going over to the contractor’s office today to co-ordinate. Just a few small things and confirming that we are all on the same page because its easier to make sure that things are aligned at the drawing stage rather than later on!

I have to also confirm the window size so I can order it from the same people who did the rest of the windows in the house. I am glad I waited to order it now as with a few changes, I think the width of the window changed and once you take possession of the goods, its not like you can return them.

On another note, I secured someone to take away the kitchen! I used this online board called FreeTOrecycle (which is a Yahoo Group) and put all the cabinets, etc (and the dishwasher) up and a fellow contacted me and said that this was exactly what he was looking for and will rent a truck to pick them up when we take them out at the end of the month. Its great because I didn’t want them going to the landfill if someone else could use them.

We also started packing away things from the rest of the main floor, because with the new floor going in, everything has to be out of the way for the floor removal and the new subfloor and 3/4″ hardwood installation. I met with the flooring contractor last week and he said that it would be 3 days to do all the work, which seems pretty quick, but hey lets be optimistic at this point!

So, all that being said, I have a few things to do to get everything kickstarted, but can’t wait to get this project underway!


We have contract!

Posted by Jeffrey on Feb 23, 2009

We got a draft copy of the contract today and after a few revisions, will be able to start the project! [Of course the first thing is putting a deposit down, but after that we will start.]

So now that we have pretty much locked down the scope of work, we have to figure out how to schedule the work to make the most sense. Because we are doing not just the kitchen, a few things have to happen first. Of course the floor will have to be done before the cabinets go in, but even before that the window should be removed and the new opening cut.

So I am using this online project planning software called wrike to help me get a sense of what order things need to happen. Now I just have to pass it by the contractor to see if it makes sense.


1 comment - Latest by:

Getting closer to starting kitchen renovation

Posted by Jeffrey on Feb 22, 2009

Its been a while since the last post and most of the time has been going over budget with the contractor and figuring out where to save a few dollars. I will do a few things that will save some money like taking up the old vinyl tile  in the kitchen and removing the cabinets and countertop, but really the big ticket items I am leaving to the pros.

We will have a lot of work to do just packing up the whole main floor of the house and finding somewhere to store the stuff because we are replacing all the hardwood throughout. I think we will take the opportunity to purge some stuff we’ve been hanging on to for a while which will help once we need to put it all back! [It will seem like we have increased our storage space!]

We agreed to move forward with this company who have been really great about going through the quote very thoroughly with us and even bringing in his subs to visit the house and discuss their work! So now we have to go and sign the contract and leave a deposit to begin the detailed  investigation for a few more areas, such as removing the current window and moving the opening over so we can get a proper run of uppers in.

Once this is done, I will order the window and hope there are no delays in getting it fabricated!